Terra-Turner Waterline Replacement Project Update for the Week of 7/01/2024
Terra-Turner Waterline Replacement Project Update for the Week of 7/01/2024
Terra-Turner Waterline Replacement Project
Main construction activity and items to watch for:
The Contractor will continue work as follows:
- Cutting asphalt around valve boxes in the streets and installing concrete collars
- Clean up
Planned location of construction and road closures for week of 7/1:
All streets are open
Work will be spread out throughout the site
Access:
Terra Ave:
Street is open to local through traffic. Please watch for crews installing concrete collars and follow cones and signage.
Sheridan Ave:
Street is open. Please watch for crews installing concrete collars and follow cones and signage.
Riverside:
Street is open. Please watch for crews installing concrete collars and follow cones and signage. There may be some activity preparing for a future closure east of the intersection with Terra for a concrete valley pan installation.
Businesses that may experience a water shutoff – to be coordinated with separate notice.
None. All waterline is installed!
Other items of note to watch for:
Please try to limit parking on the streets.