Delay to Halls Road works
The installation of a new parallel crossing on Halls Road is taking longer than anticipated. To help keep things moving and reduce disruption, we changed how we work to make sure traffic can still flo
Kingswood walking and cycling improvements
The installation of a new parallel crossing on Halls Road is taking longer than anticipated. To help keep things moving and reduce disruption, we changed how we work to make sure traffic can still flow, people can get to Lidl, and residents can park.
We’ve also run into a few unexpected issues. We had to dig deeper than planned because of an old road surface underneath, and we’ve had to work carefully around a low voltage cable that powers the crossing.
Because of these challenges, the work will now take an extra three weeks. We’re aiming to have everything completed by 21 November.
Thank you for your patience while we get this done.
The planned overnight road closures for resurfacing and carriageway markings will also be rescheduled to 19, 20 and 21 November, with the parallel crossing becoming operational on 22 November.
We do apologise for the inconvenience of these ongoing works, but we are working hard to get them completed as quickly as possible.
Once these works have been completed, we will continue with improvements on Cecil Road between the pelican crossing and South Road (Southern side). This next phase will consist of narrowing the footway on the Southern side to take account of the widening works that are planned for the Northern for a three-meter wide shared-use footway and cycleway. Further details and timelines will be shared closer to the start of these works.
Funding for this project was secured by the West of England Mayoral Authority from Active Travel England.