Update on A4174 Ring Road Resurfacing Works

Due to prolonged periods of heavy rain, the original resurfacing works scheduled to finish on 19 December will now be extended until 24 December. We have completed the majority of the works but final

A4174 Avon Ring Road improvements

Due to prolonged periods of heavy rain, the original resurfacing works scheduled to finish on 19 December will now be extended until 24 December. We have completed the majority of the works but final finishing will take place in the extra few days. 

We’re also incorporating essential maintenance on a different section of surfacing that required attention. Although this area is outside the A4174 works, carrying out the repairs during these closures helps avoid further disruption later.

We appreciate your patience and understanding as we improve the A4174. Overnight closures will continue between 7pm and 6am, with diversion routes in place.

Please check with your bus operator for any changes to services.

This project is funded by the Department for Transport through the City Region Sustainable Transport Settlement and is managed by the West of England Mayoral Combined Authority.