Bradley Stoke Way works for 2026
Throughout 2026, roadworks will be in place between Savages Wood Roundabout and Aztec West Roundabout. Work will take place in stages, and we will update our website regularly so that you know what to
A38, Alveston Hill and Bradley Stoke Way active travel improvements
Throughout 2026, roadworks will be in place between Savages Wood Roundabout and Aztec West Roundabout. Work will take place in stages, and we will update our website regularly so that you know what to expect in each upcoming phase.
Work will restart on Friday 9 January 2026 and is expected to continue until the end of the year. Once complete, these improvements will provide safer cycling, walking and wheeling options, improved facilities for bus passengers and give residents greater confidence to use active travel.
We recognise the impact of ongoing works on communities and would like to reassure you that we are doing everything we can to deliver works on time and with as little disruption to residents as possible. Thank you for your patience.
January to December 2026: Planned works
Below, we outline the works planned to take place between January and December 2026 on:
- Bradley Stoke Way (between Savages Wood Roundabout and Patchway Brook Roundabout)
- Savages Wood Roundabout
- Patchway Brook Roundabout
In our next update, we will provide information about upcoming works at two further locations: Bradley Stoke Way (between Patchway Brook Roundabout and Aztec West) and Aztec West Roundabout.
Bradley Stoke Way (Savages Wood Roundabout to Patchway Brook Roundabout)
9 to 16 January 2026:
- Works: Overnight closure of Bradley Stoke Way, between Savages Wood Roundabout and Patchway Brook Roundabout, for 7 consecutive nights.
- Time of works: Overnight only, between 8pm and 6am.
- Purpose: To prepare for the next stage of work, including installation of safety barriers and temporary road markings.
- Impact: No impact on traffic during the day, however possibility of delays overnight (between 8pm and 6am). The pedestrian path will be closed and the recommended diversion route for all path and road users will be via Savages Wood Road and Brook Way (and vice versa).
- Noise: Moderate noise and some vibration expected.
9 January to end of September 2026
- Works: Installation of segregated cycle track, footway and new crossing facilities between Savages Wood Roundabout and Patchway Brook Roundabout. Work will take place within the bus lane to allow two-way traffic to flow.
- Time of work: Mainly daytime working, occasional overnight works.
- Impact: Minimal impact expected for drivers. The pedestrian path will be closed until September 2026, with a recommended diversion route in place via Brook Way (see Map 1). Bus service routes will be unaffected, but we will need to temporarily close bus stops to complete the works. Please visit the First Bus website for the latest bus travel information.
- Noise: Moderate noise and vibration expected.

Savages Wood Road
9 to 13 January 2026
- Works: Overnight closure of Savages Wood Road junction with Savages Wood Roundabout for 4 consecutive nights. No entry or exit to the roundabout from Savages Wood Road.
- Time of works: Overnight only, between 8pm and 6am.
- Purpose: To prepare for the next stage of work, including installation of safety barriers and temporary road markings.
- Impact: No impact on traffic during the day, however possibility of delays overnight (between 8pm and 6am). Diversion is via Savages Wood Road and Brook Way (and vice versa).
- Noise: Moderate noise and some vibrations are expected.
13 January to 29 March 2026
- Works: Road closure of Savages Wood Road (westbound only) at the junction of Savages Wood Roundabout for installation of the shared use path and toucan crossing.
- Time of work: Mainly daytime working, occasional overnight works.
- Impact: No access for vehicles from the roundabout to Savages Wood Road. Diversion in place via Brook Way. Exit from the Savages Wood Road to the roundabout is unaffected.
- Noise: Moderate noise and vibration are expected.
Bowsland Way
9 to 13 January 2026
- Works: Overnight closure of Bowsland Way junction with Patchway Brook Roundabout for 4 consecutive nights. No entry or exit to the roundabout from Bowsland Way.
- Time of works: Overnight only, between 8pm and 6am.
- Purpose: To prepare for the next stage of work, including installation of safety barriers.
- Impact: No impact on traffic during the day, however possibility of delays overnight (between 8pm and 6am). Diversion is via Pear Tree Road, Woodlands Lane and Trench Lane.
- Noise: Moderate noise and some vibrations are expected.
13 January to 1 March 2026
- Works: Road closure of Bowsland Way (eastbound) at the junction of Patchway Brook
- Roundabout for installation of footpath, cycle track and puffin crossing.
- Time of work: Mainly daytime working, occasional overnight works.
- Impact: No access for vehicles to Bowsland Way from the roundabout. Diversion in place via Pear Tree Road, Woodlands Lane and Trench Lane (see Map 3). Entry to the roundabout from Bowsland Way is unaffected.
- Noise: Moderate noise and vibration expected.

Information for bus users
Changes may be made to scheduled services because of these works. Please visit: www.firstbus.co.uk for the latest bus travel information.
Stay Informed
Follow our projects to get notified of upcoming engagements and the latest project related news.