Traffic management (Alveston Hill)

Diversionary routes while construction work is underway.

A38, Alveston Hill and Bradley Stoke Way active travel improvements

Construction updates

October 2026 upate

We are due to start the next phase of construction work at Streamleaze, Thornbury, on 12 October.

Until 14 December, we will be resurfacing part of the road, replacing the existing speed bumps with a new speed table, installing a pedestrian crossing at the junction with Rock Street and improving the footpaths.

Overnight traffic management will be in place during the works, including full road closures at certain times.

You can read the full details here.

Below is a link to the engineering drawings where you can review the improvements planned for Streamleaze. 

Engineering drawings for Streamleaze works

Summer 2026 update

We are pleased to confirm that the works on Thornbury Road / Alveston Hill B4061 are  complete.  We appreciate the patience shown by local residents and businesses throughout the construction period.

Our contractors have now removed the temporary blocks that were in place along a short section of the shared-use path beyond the toucan crossing, restoring the path to its full width. We recognise that the area currently has an unfinished appearance, and our teams will return during the greenfield works to apply a permanent finish around the new retaining structure.

A map displaying the construction phases can be found below.    

To get latest updates on highways projects, straight to your inbox, you can register for our highways e-newsletter.   

This project is funded by the Department for Transport through the City Region Sustainable Transport Settlement and is managed by the West of England Mayoral Combined Authority. 

Map showing phasing of construction work on the A38