Works on A38 and Alveston Hill from 2 February 2026
Work is on schedule on the A38 and Alveston Hill to deliver active travel and public transport improvements. We would like remind you of the next phase starting on 2 February 2026, and want to inform
A38, Alveston Hill and Bradley Stoke Way active travel improvements
Work is on schedule on the A38 and Alveston Hill to deliver active travel and public transport improvements.
We would like remind you of the next phase starting on 2 February 2026, and want to inform you about how to travel in and out of Alveston and the surrounding area during overnight road closures on the A38 Gloucester Road and Thornbury Road.
Closure details
A38 Thornbury Road junction, Alveston:
- Dates: 2 February to 22 February 2026
- Times: Overnight from 8.00pm to 6.00am
- Location: A38 from the junction with Greenhill to just past Berkeley Vale Motors. In addition, from the Berkeley Vale Motors junction down along the B4061 Thornbury Road and part of Alveston Hill, see the map below for details.
Alternative routes
The alternative route in/out of Alveston is:
• Access from the Bristol direction: Fern Hill, Lower Tockington Road, Upper Tockington Road, Haw Lane and Alveston Road and vice versa
We strongly recommend that drivers do not attempt to access Thornbury via Mumbleys Lane and Sweet Water Lane, or the A38 via Washingpool Hill Lane. These are narrow and unlit rural lanes that are unsuitable for large volumes of traffic, particularly in winter conditions as they are untreated.

We apologise for any disruption and inconvenience caused by these works and appreciate your patience and understanding.
For all closures:
- Access: There will be no through access for motor vehicles during the closures, as works will be taking place across the full carriageway to ensure the safety of staff on site. There will be no access overnight on Alveston Hill for pedestrians or cyclists for safety reasons. Residents will have limited access to their properties. There may be delays while the work crew ensures safe access.
- Noise: Noise and vibration are expected during the works. The materials need time to set in the early morning, so there shouldn’t be noise for the full duration.
- Schedule: If unforeseen circumstances such as severe weather, utility issues, or supply delays occur, works may be affected. Updates will be posted on the on this website and our StreetCare Facebook page.
This project is funded by the Department for Transport through the City Region Sustainable Transport Settlement and is managed by the West of England Mayoral Combined Authority.