A432 Badminton Road Works - Nibley Lane to the Culvert Avenue Roundabout – works recommencing
Improvement Works on the A432 Badminton RoadSignificant improvement works are planned along the A432 Badminton Road as part of the City Region Sustainable Transport Settlement (CRSTS) project. These u
A432 Travel Improvements
Improvement Works on the A432 Badminton Road
Significant improvement works are planned along the A432 Badminton Road as part of the City Region Sustainable Transport Settlement (CRSTS) project. These upgrades will support safer, more accessible and more sustainable travel between Yate, Coalpit Heath and the A4174.
Improvement works are now restarting on the section of the A432 Badminton Road - Nibley Lane to the Culvert Avenue Roundabout (Sec 7) and may affect travel and access at various times. These works were postponed due to poor weather.
When and Where
- Start date: Recommenced w/c 16 March 2026
- Duration: Approximately 12 weeks
- Location: A432 Badminton Road from its junction with Nibley Lane to the roundabout junction with Culvert Avenue
- Working hours: 8pm–6am for much of the activity
- Working days: Overnight works throughout
Traffic Management
- Duration of works: Temporary Narrow lanes, with overnight traffic lights.
- Noise: Higher noise levels expected overnight, but we will aim to keep this to a minimum so as to reduce disruption.
Summary of Improvements and Local Considerations
Across this section, the works will deliver:
- New segregated footpaths and cycle lanes
- Improved junction layouts and clearer road configurations
- Safer pedestrian and cyclist crossings
- Enhancements to walking, wheeling, cycling and bus stop facilities
- Resurfacing of the existing cycle track (Nibley to Culvert Avenue) using green asphalt
In response to feedback from residents, drop in sessions and the parish council:
- Access to private property will be maintained, although short delays may occur when work is taking place directly outside driveways etc. Our engagement team and workforce will liaise with you directly during these periods and attempt to keep any disruption to a minimum.
- Access to side roads will remain open where practicable
- Crossing facilities will be upgraded or added throughout the route
This project is funded by the Department for Transport through the City Region Sustainable Transport Settlement and is managed by the West of England Mayoral Combined Authority.
Thank you for your patience and cooperation while these essential improvements take place.