Where we're working

See where the work will take place and what we're doing to minimise disruption.

Yate Spur active-travel scheme

Work locations

The Yate Spur scheme will improve walking and cycling provision, making it easier and safer for everyone to walk, cycle or wheel between Yate and Westerleigh village and beyond. 

Some sections have already been completed. Section 6, the final on-road link into Yate will be constructed in two phases, starting from July 2026. The works will have a temporary impact on journey times whilst construction is taking place.

Phase 1

  • Commencing Monday 27 July 2026

  • Diversion from the Westerleigh Road junction with Shire Way at the roundabout to the Rodford Way/Road to Nowhere roundabout and along Shire Way to Brockworth

Phase 1 traffic management map

Phase 1 temporary traffic management: 

  • Full 24-hour closure to northbound traffic, with vehicle access maintained for southbound traffic, until 20 December.

  • Northbound traffic will be diverted via Shire Way, with clearly signed routes in place. Pedestrian access will remain unaffected.

  • Residents of Chedworth and Rodborough will only be able to access and exit their street from the southbound direction of Shire Way.

  • Works will primarily take place during the day to help minimise noise disturbance to residents. 

  • Overnight full closures of the northbound and southbound carriageway from 21 to 25 October to install underground ducting for the new pedestrian crossings (8pm to 6am)

  • Overnight full closures of the northbound and southbound carriageway to carry out resurfacing works and remove traffic management measures 7 December to 20 December (8pm to 6am).

  • We will do everything we can to minimise noise and vibration during overnight works but some disruption is likely and we apologise for this. 

  • Access to all side streets and properties will be maintained. There may occasionally be short delays while operatives ensure safe access.

  • The existing footpath on the west of the carriageway will be closed for the duration of the works. Temporary signals will be installed on the existing uncontrolled pedestrian crossing immediately south of the Chedworth junction to allow pedestrians to cross safely.

  • The northbound bus service will be diverted during the works. The southbound service will continue to operate as normal. Passengers are advised to check with public transport operators. 

We understand these works will cause disruption. We apologise for this inconvenience while we make significant improvements to the area. We will do everything we can to minimise the impact of the works. 

Phase 2

Phase 2 will see the completion of a shared-used pathway path between the mini-roundabout near the viaduct and the Nibley Lane junction along Westerleigh Road.

Please note that this phase does not include the proposed pedestrian crossings at the Westerleigh Road/Nibley Lane junction, which will be delivered as part of a later stage of the scheme.   

Phase 2 temporary traffic management:

  • Overnight temporary traffic signals from 26 October to 20 December (8pm to 6am).

How we’re managing disruption

During construction we will:

  • Maintain pedestrian access at all times
  • Maintain access to homes and side roads, with occasional short delays for safety
  • Provide clear diversion routes and advance warning signage
  • Use overnight works only where essential to install/remove traffic management

If you have a query relating to this project please contact us via email: Yate.Spur@southglos.gov.uk