Calder Way Improvements
Welcome to the Calder Way Project Website!
The Borough of State College is delighted to present the Calder Way Project, a focal point within the esteemed Downtown Master Plan. The vision is to transform this corridor into a pedestrian-preferred enclave, reducing vehicular traffic and enhancing the overall urban experience.
Project Overview:
- Vital utility improvements, including sanitary sewer, storm sewer, water, gas, electric, and telecommunications systems.
- Replacing conventional curbed sidewalks with captivating artistic measures.
- Introducing streetscape enhancements from Hiester to Burrowes.
- Phase 2 – Utility Construction (S. Fraster to S. Atherton), January 2026 – July 2026
- Phase 2A- Utility Construction (Hetzel St. Intersection), March 2026 – July 2026
- Phase 3 – Design 2026 (McAllister to S. Garner), Utility Construction 2027
Future Phases - 2026 to 2027:
- Utility replacements in remaining segments.
- Streetscape elements integrated post-utility replacement from Hiester to Burrowes.
Grants and Feasibility Study:
- SEDA COG previously awarded a $60,000 grant (with a $90,000 Borough contribution) for the Calder Way Infrastructure Feasibility Study. This study provided comprehensive insights into the project's scope and costs, informed by the construction endeavors.
- Phase 2 and Phase 2A recevied $2.75 million H20 PA Grant for sewer, storm, and water improvements.
- Phase 3 secured $16 million Safe Streets and Roads for All Grant for design and construction.
- Pursuing state and federal grants for forthcoming project segments.
Follow this Transformative Journey:
- Stay updated on project milestones and progress.
- Engage with the community as Calder Way is rejuvenated into a more refined, sustainable, and interconnected urban landscape.
Project Contacts
Calder Way Public Relations: Tristan Klinefelter
(814) 680-4468 | tklinefelter@statecollegepa.us
Director of Public Works: Sam Robbins
(814) 234-7100 | srobbins@statecollegepa.us
Tentative Project Timeline
Bid Opening Date
Council Approval
Construction Begins - Phase 2
Project Updates
Calder Way Project Phase 2A Update (April 2)
Calder Way Project Phase 2 Update (April 2)
Calder Way Project Phase 2A Weekly Update (March 26)
Calder Way Project Phase 2 Update (March 26)
Calder Way Project Phase 2 Update (March 19)
Calder Way Project Phase 2A Weekly Update (March 19)
Calder Way Project Phase 2A Weekly Update (March 12)
03-12-26 Update on Calder Way Project Phase 2A
Calder Way Project Phase 2 Weekly Update (March 12)
03-12-26 Update on Calder Way Project Phase 2
Calder Way Project Phase 2A Update (March 5)
03-05-26 Update on Calder Way Project Phase 2A
Calder Way Project Phase 2 Update (March 5)
03-05-26 Update on Calder Way Project Phase 2
Calder Way Project Phase 2 Update (February 26)
02-26-26 Calder Way Phase 2 Project Update
Calder Way Project Phase 2 Update (February 19)
02-19-26 Calder Way Phase 2 Project Update
Calder Way Project Phase 2 Update (February 5)
02-05-26 Calder Way Phase 2 Project Update
Calder Way Project Phase 2 Update (January 29)
01-29-26 Calder Way Phase 2 Project Update
Calder Way Project Phase 2 Update (January 27)
01-27-26 Update on Calder Way Project Phase 2
Calder Way Project Phase 2 Update (January 26)
01-26-26 Update on Calder Way Project Phase 2
Calder Way Project Phase 2 Update (January 25)
01-25-26 Update on Calder Way Project Phase 2
Calder Way Project Phase 2 Update (January 22)
01-22-26 Update on Calder Way Project Phase 2
Calder Way Project Phase 2 Update (January 15)
01-15-26 Update on Calder Way Project Phase 2