Estimated Cost: $1,495,532.00
Estimated Start Date: Summer 2025
Estimated Completion Date: Spring 2026
Project Description: This in-house design project focuses on roadway and drainage infrastructure improvements along Westwood Blvd East, from NW 94th Ave/Westwood Blvd to W. McNab Road. The improvements aim to enhance drainage systems, improve roadway conditions, and address water ponding issues. Key components include asphalt reclamation, drainage upgrades, curbing, sidewalk enhancements, speed hump installations, ADA ramps, and swale restoration, ensuring compliance with all applicable regulations.
Status: The project is in the preliminary design and permitting stage, involving field data collection, analysis, surveying, and testing. It is tentatively scheduled to go out for bid in Summer 2025.