Tampa, FL
Photo crews working on road.

Lois Avenue Water Main Replacement Work

The City of Tampa is committed to providing high-quality, reliable water service for drinking, cooking, cleaning, sanitation, irrigation, recreation, business, and fire protection. As part of our ongoing investment in the water distribution system, crews are replacing aging pipelines to strengthen system reliability and better serve our community.

As part of this effort, the Water Engineering Construction Team will replace water mains along South Lois Avenue between West Azeele Street and West Dale Street. This project includes the replacement of more than 800 linear feet of water main that has been in service since the 1940s. The work will also involve transferring existing water services, roadway resurfacing, and maintenance of traffic to ensure safe access through the construction area.

Replacing these aging water mains will improve overall water service reliability by reducing leaks and service interruptions caused by main breaks. The new infrastructure will also increase system capacity and improve water pressure for nearby homes and businesses.

We appreciate your patience and support as we work to enhance water service in your neighborhood.

Frequently Asked Questions

How long will construction last?

Pipe replacement work is expected to take approximately two months. Crews are expected to clear the neighborhood by mid-March 2026.

When will work take place?

Water main replacement work will take place over the course of two months. Crews will work Monday through Thursday, 8am to 3pm. During the course of the work, residents along the impacted area will be able to enter and exit their homes.

Will my water service be interrupted?

Interruption of water service may occur but is expected to be minimal and of short duration as services are transferred to the newly installed pipes. Property owners will be notified in advance of all scheduled interruptions of service.

Will I experience an interruption in mail delivery or garbage/recycling collection?

Crews will work to will work with service providers so that they can access the area during construction activities. Any service interruptions should be reported by calling the project hotline at (813) 557-3979, or emailing WaterPublicNotice@tampa.gov.

Contact Information

Email: WaterPublicNotice@tampa.gov
Phone: (813) 274-5122

Map shows location of water main work.

Stay Informed

Get notified on upcoming engagements and the latest project related news.

"This important investment will strengthen water infrastructure, improve service reliability, and help meet the community’s needs for years to come. We appreciate your patience and cooperation as we complete these improvements that benefit the entire neighborhood. "

Construction Schedule

Construction Starts
January 12
Construction at 50% Completion
Mid February
Construction Ends
Mid March 2026