Palma Ceia Water Main Improvements Phase III

The City of Tampa is working hard to build, maintain, and deliver high quality, reliable water service to its customers for drinking, cooking, cleaning, sanitation, irrigation, recreation, business, and fire protection. The City's Capital Improvement Program (CIP) identifies and delivers projects throughout Tampa where water infrastructure, treatment, and distribution system improvements are needed. This project is one of many City projects funded by the PIPES initiative.

As part of the City's CIP, the Palma Ceia Water Main Improvements Project will improve water service reliability by replacing aging water mains and reducing service interruptions due to breaks and leakage. The new water mains will also add capacity needed for growth and increase water pressure for homes, businesses and fire suppression throughout the Palma Ceia area. The project will replace approximately 31,700 linear feet of existing water main pipes with new and larger diameter pipes ranging from two (2) to twelve (12) inches and includes the transfer of existing services, temporary water service, roadway resurfacing and restoration, sidewalk and driveway restoration, maintenance of traffic, and sodding.

Project Location

The Palma Ceia Water Main Improvements Project Phase III will replace water main pipes in the city's right-of-way located on streets throughout neighborhoods in Palma Ceia, including the Palma Ceia Neighborhood Association, New Suburb Beautiful, and Golfview. The project area also includes a portion of the Palma Ceia commercial district, which connects local businesses to adjacent and nearby neighborhoods.

Frequently Asked Questions

What does the project include?

The project includes the replacement of aged and/or undersized pipes with new water main to meet current demands in your area. This project will include transferring customers’ existing meters to the new water main and installing new and/or additional fire hydrants to increase local fire protection capability.

Will my water service be interrupted?

Interruption of water service may occur but is expected to be minimal and of short duration as services are transferred to the newly installed pipes. Property owners will be notified in advance of all scheduled interruptions of service through door-hanger notifications or other means of communication.

Will I experience an interruption in mail delivery or garbage/recycling collection?

To avoid/minimize impacts to mail delivery and garbage/recycling pick-up, the contractor will work to coordinate with service providers concerning construction activities. Any service interruptions should be reported by calling the project hotline at (813) 557-3979, or emailing WaterPublicNotice@tampa.gov.

Contact Information

Email: WaterPublicNotice@tampa.gov
Phone: (813) 557-3979

Map of Current Water Pipeline Work and Road Restoration Progress

A map showing water pipeline work and road restoration work in the Palm Ceia neighborhood within the following perimeter: North of West Grenada Street, East of South Himes Avenue, South of West Morrison Avenue, and West of South Habana Street.

Stay Informed

Get notified on upcoming engagements and the latest project related news.

Weekly Construction Schedule

West San Carlos Street; South Marti Street
July 1
West San Carlos Street; South Marti Street; West Barcelona Street; South Concordia Avenue; West Granada Street; South MacDill Avenue; West Aquilla Street
July 8
West Aquilla Street and South Marti Street; West Carlos Street
July 15

Project Updates

Important Dates

1
Jul 2025

Construction Resumes

Water main work begins. Crews to start along West San Carlos Street. Crews will also make additional temporary patch roadway repairs on South Marti Street.

25
Jul 2025

New Map & Timeline

Residents will receive updated restoration map with details on street repairs, as well as a tentative timeline on restoration work.

18
Aug 2025

S MacDill Avenue Closures

Our contractors are continuing to finish up the remaining water infrastructure work on the project. As part of this work, portions of South MacDill Avenue will be intermittently closed between August 18, 2025, and August 29, 2025.

Closure Schedule (9 a.m.–4 p.m., Mon–Fri):
🚧Aug 18–20: Right southbound lane closed at S MacDill Ave & W Sunset Dr
🚧Aug 20–22: Right northbound lane closed at S MacDill Ave & W San Isidro St
🚧Aug 25–29: Right northbound lane closed at S MacDill Ave & W San Carlos St

Traffic flaggers will be in the area to direct traffic. Crews will return to the area mid-September for final paving work.

We thank you for your patience as we work to bring this project to a successful close.

22
Aug 2025

S MacDill Ave Closure Update

Due to a water main break at S MacDill Ave and W Sunset Dr, the contractor has updated the lane closure schedule to accommodate additional repair work. Please see the revised schedule below:

Lane Closure Schedule
(🕔Monday–Friday, 8:00 a.m. – 5:00 p.m.)
🚧 Friday, August 22
o Right northbound lane closed at S MacDill Ave & W San Carlos St
🚧 Today through Thursday, August 28
o Right southbound lane closed at S MacDill Ave & W Sunset Dr
🚧 Monday, August 25 – Friday, August 31
o Right northbound lane closed at S MacDill Ave & W San Isidro St

Traffic flaggers will be on-site to assist with traffic flow and ensure safety in the work zones.

25
Aug 2025

Permanent Roadwork Restoration Begins

15
Sep 2025

Palma Ceia Water Main Improvements Project Nearing Completion

The Tampa Water Department is excited to announce that the final phase of the Palma Ceia Water Main Improvements Project is expected to wrap up within the next three weeks—weather permitting.

Over the coming weeks, our contractor will be completing paving work across several key areas, including:

🔹 W San Jose St (from S Obrapia St to Selmon Expressway)
🔹 S Exmoor St & W San Isidro St
🔹 Portions of S MacDill Ave
🔹 Portions of W Granada St (from S Himes Ave to S MacDill Ave)
🔹 Barcelona St near S MacDill Ave
🔹 Portions of W San Rafael St, west of S MacDill Ave
🔹 Additional paving improvements on S Marti St

🧱 Crews will complete final brick restoration along parts of W San Isidro St, W San Carlos St, and W Granada St.

Since taking over in June, our new contractor has worked hard to bring this project to a smooth and timely finish. If all stays on schedule, all crew members and construction equipment associated with this project will be out of the neighborhood by the first week of October. The finish line is in sight!

25
Sep 2025

Brickwork Restoration Update

Contractor crews are hard at work this morning, restoring the majority of the remaining brickwork — including all brickwork along West San Carlos Street — with completion expected by Friday. 👷‍♀️🧱

Next up: crews will complete the final brickwork along South Exmoor Street & West San Miguel Street as well as South Esperanza Ave & West Palmira Ave next week.

We’re happy to report that the Palma Ceia Water Mains Improvement Project remains on schedule, with all work expected to wrap up by the first full week of October. ✅

Thank you to our Palma Ceia neighbors as we wrap up this important work!

13
Oct 2025

Final Checks

Both City and Kiewit teams are completing final quality checks in the neighborhood ✅
Despite the original contractor defaulting, Kiewit stepped in and wrapped up the final phase in just 4 months — helping improve water service, update old pipes, and reduce future water main breaks 💧
If you have any questions or concerns, please email WaterPublicNotice@tampagov.net or call our hotline (813) 557-3979.
Thank you for your support! 🙌