Visit West Sacramento, CA Homepage
October update
Project

October update

October Update

Neighborhood Pavement Preservation & Arterial Streets Pavement Repair Project

  • Slurry seal surface treatment ongoing and being applied at various locations within the project limits (In Progress)
  • Installation of striping and pavement markings. (In Progress)
  • Type III microsurface treatment to be applied on Southport Parkway between Lake Washington Blvd and Ramco St, anticipated date 10/24/23 to 10/25/23. Expect delays (Next)
  • Type III microsurface treatment to be applied on Jefferson Blvd between Davis Rd and Southport Prkwy, anticipated date 10/26/23. Expect delays (Next)
  • Emergency response will remain unaffected. Postage, Waste Services, Bus will remain on schedule unless otherwise noted.
  • Please note for garbage pickup days, residents can leave their garbage at regular curb location. Construction crew will relocate during work.