Eccleston Street Public Realm Improvements

Eccleston Street Public Realm Improvements

These proposals build on successful elements of outdoor dining and increased greening that were introduced to Eccleston Street in 2020 on a temporary basis. Works are commencing on site on 11th June 2026.

See below for more information.

About the project

Email

It is possible that the works date may slip for operational reasons such as weather delays between now and the planned start date but the methodology of carrying out the work is not expected to change. Should there be a change to the methodology or significant change to the programme, we shall inform you at the earliest opportunity. Pedestrian access to properties will be maintained at all times.

The basement/vault to your property is a separate structure from the public highway and keeping it in a watertight condition is the responsibility of the owner or freeholder. If the vault/basement has not been properly damp proofed and/or tanked it is not secure from water ingress. Please be advised that neither the Service Provider or the City Council will be responsible for any damage resulting from water ingress in such circumstances.

We do apologise in advance for any inconvenience that these works may cause, we shall endeavour to keep noise disruptions to a minimum.

Should you require further information, or any reasonable adjustment, please do not hesitate to contact Robert Burton, the public liaison officer for this scheme. He can be reached on 07760 962103 or by email at robert.burton@fmconway.co.uk.

Timeline

Temporary scheme implemented on Eccleston Street

2020

WCC consultation on the temporary scheme

August 2021

Public Consultation

8th July 2024 - 9th August 2024
Seeking feedback on the latest design proposals for Eccleston Street public realm scheme

Drop-in Event

11th July
Midday to 2pm - 23 Eccleston Street

Drop-in Event

6th August
5pm until 7pm - 23 Eccleston Street

Develop detailed designs taking into account feedback received

Autumn 2024 - May 2025

Construction of permanent scheme begins

June 2026

Project close out

December 2026

News

F.M. Conway Ltd have been commissioned on behalf of Westminster City Council to undertake public realm improvement works on Eccleston Street. The works will commence on 11th June 2026 for an estimated 6-month programme.

The works include footway and carriageway re-construction along the extents of Eccleston Street between Buckingham Palace Road and Ebury Street, including sections on Ebury Street and Eccleston Place. The construction works will be delivered in phases to maintain accessibility along the entire length of the road throughout the duration of the project. Approximate phasing is detailed below:

  • Phase 1 (Jun) – Eccleston Street southern footway (Buckingham Palace Road – Eccleston Place)
  • Phase 2 (Jun – July) – Eccleston Street northern footway (Buckingham Palace Road – Eccleston Place)
  • Phase 3 (July – Sept) – Eccleston Street southern footway (Eccleston Place – Ebury Street)
  • Phase 4 (Sept – Nov) – Eccleston Street northern footway (Eccleston Place – Ebury Street)
  • Phase 5 (Nov – Dec) – Eccleston Street/Eccleston Place Junction (Road Closure)
  • Phase 6 (Dec/Jan TBC) – Eccleston Street Resurfacing

In order to undertake the works safely, the closure of Eccleston Street/Eccleston Place will be required during Phase 5. Appropriate diversion routes will be marked on site.

Meet the team

Westminster City Council
Westminster City Council

Westminster City Council is responsible for running this consultation, analysing its results and presenting them to stakeholders and the public.

Read Westminster City Council privacy policy

Grosvenor
Grosvenor

Grosvenor's heartland is in London’s Mayfair and Belgravia, where we support over 1,000 businesses and thousands of residents, workers and visitors each day. We are partnering with Westminster City Council on this consultation for Eccleston Street.

Read Grosvenor privacy policy

Contact Team

Should you require further information, please do not hesitate Robert Burton, the public liaison officer for this scheme.

Call 07760962103