Warwick Way Construction Updates - 01/08/25
Phase 1 Warwick Way (between Upper Tachbrook Street and Wilton Road)Works are complete for Phase 1 with the exception of the installation of setts and chamfered to the loading bay outside Tesco.  
Warwick Way Town Centre Highways Scheme
Phase 1 Warwick Way (between Upper Tachbrook Street and Wilton Road)
Works are complete for Phase 1 with the exception of the installation of setts and chamfered to the loading bay outside Tesco. A temporary asphalt construction has been installed in this location to mitigate delays to materials. Installation of the permanent materials will align with the resurfacing of Warwick Way in October. Warwick Way has been made one-way westbound between its junctions with Upper Tachbrook Street and Belgrave Road with temporary road markings installed to inform road users.
Phase 2 Denbigh Street
The works on Denbigh Street are now complete with the exception of the permanent resin bound finish to the tree pit which will be completed in the coming weeks.
Phase 3 Wilton Road
The traffic signals at the junction have now been installed and commissioned by TfL.
Phase 4 Warwick Way (between Wilton Road and Guildhouse Street) and Phase 5 Warwick Way (between Guildhouse Street and Belgrave Road)
The footway widening and paving has progressed along Warwick Way towards Belgrave Road with works now being carried out between Guildhouse Street and Belgave Road. These works are due to be complete in mid August.
Phase 6 Upper Tachbrook Street (between Longmoore Street and Warwick Way)
The footway will be widened the west side of Upper Tachbrook Street. Works are due to start on 18th August.
Churton Street and Tachbrook Street
Works have so far focused on the Warwick Way element of the project but construction of the Churton Street proposed scheme will start from 18th August running in tandem with the works on Upper Tachbrook Street. Our Public Liaion Officer, Bob Burton, will visit residents and businesses in the build up to the works starting on site to update them on the upcoming works. Works to the junction with Tachbrook Street and Charlwood Street will commence in January 2026.
Further information:
If you have any questions while works are taking place on-site, please contact our Public Liaison Officer, Bob Burton. Bob can be reached at 07760 962103, although he may not be always on-site.
For more information on the scheme drawings and phasing plans, please visit here