Cleveland Street cycleway
We want to make it safer and more pleasant to cycle and walk in the city. The Cleveland Street section forms part of wider proposals to provide cycleways between the West End and Pimlico, and includes a number of changes to highways in the surrounding area.
This scheme is under construction.
About the project
The Cleveland Street Cycleway scheme is led by Westminster City Council in partnership with Camden Council.
In December 2021, Westminster City Council’s Cabinet Member for City Management and Air Quality approved the route of the Cleveland Street Cycleway between Maple Street and Mortimer Street. This section forms part of wider proposals to provide cycleways between the West End and Pimlico.
Westminster City Council and Camden Council want to make it safer and more pleasant to cycle and walk in (and between) both boroughs. This is part of a joint strategy to promote journeys by public transport, foot and cycle, to improve air quality and for London to become a carbon neutral city.
Safe, direct and accessible walking and cycling routes in the West End are important in achieving this.
Information

Construction
Find out more about the construction of the C63 Cycleway

You said, we did
See the results of the consultation here

Project Information
In December 2021, Westminster City Council’s Cabinet Member for City Management and Air Quality approved the route of the Cleveland Street Cycleway between Maple Street and Mortimer Street. This secti
Meet the team

Westminster City Council is responsible for running this consultation, analysing its results and presenting them to stakeholders and the public.
News

Cleveland Street Cycleway Construction Update - 12 August 2026
The Cleveland Street Cycleway is being delivered by Westminster City Council in partnership with Camden Council. Project Phasing PlanCompletion of Planned WorksPlease note that the works relating to t

Cleveland St Cycleway Construction Update – 20 July 2026
The Cleveland Street Cycleway is being delivered by Westminster City Council in partnership with Camden Council. Phasing PlanUpdate to PhasingThe current programme is:• Goodge Street to Tottenham S

Cleveland St Cycleway Construction Update - 8 July 2026
The Cleveland Street Cycleway is being delivered by Westminster City Council in partnership with Camden Council. Phasing PlanUpdate to PhasingThe current programme is:• Goodge Street to Tottenham S

Cleveland St Cycleway construction update 18/03/26
Cleveland Street Cycleway construction update - February 2026Looking back (early March 2026)Phase 1This phase is substantially complete, but the Belisha Beacons (at the new Maple St crossing, outside

Cleveland St Cycleway construction update
Cleveland Street Cycleway construction update - February 2026Looking back (early Feb 2026)Phase 1We have re-aligned the zebra crossing due to the large tree roots. The crossing point and large tree re
Team
Let's introduce you to the team
Commonplace facilitates this conversation on behalf of the team made up of the organisations listed here. The information you provide will only be used for the purposes stated in each organisation’s privacy policy.

Westminster City Council is responsible for running this consultation, analysing its results and presenting them to stakeholders and the public.