View of New Zealand House development proposals on Pall Mall and Haymarket

New Zealand House, 80 Haymarket Public Realm

Public realm improvements outside the new development at 80 Haymarket are being proposed as part of the developer's planning conditions with Westminster City Council.   

Further information on the proposal can be found below and we would be pleased to receive any comments you may have.

About the project

Email

The Developer (The Crown Estate) of 80 Haymarket is proposing highway and public realm improvements on Haymarket and Pall Mall, as part of their planning conditions (Ref: 19/07815/FULL) with Westminster City Council. These works will include improvements to both the footway and carriageway.

Westminster City Council are notifying local residents and stakeholders of these proposals and would be pleased to receive any comments, to this informal consultation, you may have.

The current proposals for the highways and public realm improvements and parking changes are indicated on below drawing and include the following:

Pall Mall

  • Conversion of the existing vehicular crossover into footway
  • Reinstatement of existing kerbs
  • Reinstatement of the existing footway material
  • Introduction of loading restrictions
  • Road markings refresh

Haymarket

  • Introduction of a new vehicular crossover
  • Reinstatement of existing kerbs
  • Reinstatement of the existing footway material
  • Relocation of the parking bay
  • Road markings refresh

Have your say

Timeline

Threshold Level Review

March 2024 - May 2024
WCC's service provider undertook review of the threshold levels submitted by the developer's consultants

Stage 1 Feasibility Design Review

November 2024 - November 2024
WCC's service provider undertook design review of the stage 1 feasibility design submitted by the developer's consultants

Stage 2 Initial Design Review

November 2025 - March 2026
WCC's service provider undertook design review of the stage 2 initial design submitted by the developer's consultants

Traffic Management Order (TMO) & Section 6 Public Consultation

May 2026 - June 2026
TMO consultation & section 6 public consultation

Stage 3 Detailed Design Review

June 2026 - July 2026
WCC's service provider is to undertake design review of the stage 3 detailed design which is to be submitted by the developer's consultants, following the TMO & section 6 consultation and incorporating any feedback received and agreed with WCC

Stage 5 Implementation Works

TBC - TBC
Highway construction works being implemented

Contact Team

In order to request hard copies of the materials or any reasonable adjustment to participate, please contact: WCC-Consultation@wsp.com. Alternatively, call Westminster City Council General Enquiries on 020 7641 6000 and they will pass your request along to the consultation team.

Call 020 7641 6000