Warwick Way Construction Updates - 07.11.2025
Phase 1-5 Warwick Way Works are complete for Warwick Way phases 1 to 5. However remaining works include tree pit reinstatement on Denbeigh Street and tree planting along Warwick Way, which will be co
Warwick Way Town Centre Highways Scheme
Phase 1-5 Warwick Way
Works are complete for Warwick Way phases 1 to 5. However remaining works include tree pit reinstatement on Denbeigh Street and tree planting along Warwick Way, which will be completed in the coming weeks.
Phase 6 Upper Tachbrook Street (between Longmoore Street and Warwick Way)
Footway works are due to be completed on the 8th November.
Resurfacing of the Carriageway
Resurfacing of Warwick Way, Upper Tachbrook Street, Denbigh Street and Wilton Road was completed as planned over three days from 14th to 16th October.
Phase 1 Churton Street (between Tachbrook Street and Charlwood Place)
All footway works have now been completed to the northwest side of Churton Place between Tachbrook Street and Charlwood Place. On the southeast side, the loading bay has been constructed except for a section outside No. 23. Until ongoing investigations related to No. 23 are concluded, the rear section of footway cannot be completed. A further update on an expected completion date for this section will be provided shortly.
Phase 2 Churton Street (between Charlwood Place and Belgrave Road)
Construction is now underway for Stage 2 of the Churton St works, drainage works started from the 5th November. Construction works expected to be completed on 19th December.
Further information:
If you have any questions while works are taking place on-site, please contact our Public Liaison Officer, Bob Burton. Bob can be reached at 07760 962103, although he may not be always on-site.
For more information on the scheme drawings and phasing plans, please visit here.