Warwick Way Construction Updates - 10.10.2025
Phase 1 Warwick Way (between Upper Tachbrook Street and Wilton Road)Works are complete for Phase 1 with the exception of the loading bay outside Tesco, works for which are currently underway with kerb
Warwick Way Town Centre Highways Scheme
Phase 1 Warwick Way (between Upper Tachbrook Street and Wilton Road)
Works are complete for Phase 1 with the exception of the loading bay outside Tesco, works for which are currently underway with kerbs having already been replaced. Granite setts will be installed next week and the footways reopened to pedestrian traffic and loading vehicles by 17th October.
Phase 2 Denbigh Street
The works on Denbigh Street are now complete with the exception of the permanent resin bound finish to the tree pit which will be completed in the coming weeks.
Phase 3 Wilton Road
The footway widening and traffic signal works for Phase 3 are complete.
Phase 4 Warwick Way (between Wilton Road and Guildhouse Street)
The footway widening works for Phase 4 are complete.
Phase 5 Warwick Way (between Guildhouse Street and Belgrave Road)
The footway works at the Belgrave Road junction have been completed and the junction with Belgrave Road has been reopened.
The western footway at the junction with Guildhouse Street has been completed. Kerbs have been completed on the east side of the junction and footway works are expected to be completed in this location by 13th October.
Phase 6 Upper Tachbrook Street (between Longmoore Street and Warwick Way)
Kerbs have been completed for this section and works are currently focused on construction of the loading and parking bays. The road will remain open during the works under southbound one-way operation as per the finished scheme. Upper Tachbrook Street as a whole is on track to be completed by 28th October.
Resurfacing of the Carriageway
Resurfacing of Warwick Way and Upper Tachbrook Street is scheduled for 14th to 16th October and will be carried out under a full closure of those roads over 3 days. A letter has been issued to residents and businesses communicating the arrangements. The resurfacing will be phased as follows:
- Phase 1(14th October) – Warwick Way (Vauxhall Bridge Road to Denbigh Street) and Upper Tachbrook Street (Warwick Way to Longmoore Street)
- Phase 2 (15th October) – Warwick Way (Upper Tachbrook Street to Belgrave Road), Wilton Road (Warwick Way to Longmoore Street) and Denbigh Street
- Phase 3 (16th October) – Warwick Way (Wilton Road to Belgrave Road)
Phase 1 Churton Street (between Tachbrook Street and Charlwood Place)
On the west side, footways and parking bays have been constructed from outside Lord City Express to the Constitution pub. On the east side, excavation for the new widened footways/ raised parking bays has progressed with sections of kerbs and setts being laid. The deep drainage connection at Charlwood Place has been completed and reinstated. Works are progressing to the rear of the footway on the southeast side. There will be a pause to works on Churton Street and the road will reopen while the resurfacing works on Warwick Way are being completed.
Further information:
If you have any questions while works are taking place on-site, please contact our Public Liaison Officer, Bob Burton. Bob can be reached at 07760 962103, although he may not be always on-site.
For more information on the scheme drawings and phasing plans, please visit here.