About the project

Email

The developer of 8-10 & 11-14 Grafton Street Development has commissioned FM Conway / WSP, Westminster City Council’s service provider, to undertake the review of their adjacent highway and public realm improvements on both Grafton Street and New Bond Street.

FM Conway Ltd / WSP are notifying residents and stakeholders on behalf of Westminster City Council of this proposal and would be pleased to receive any comments you may have by 19th March 2026.

The scheme proposal for the highways and public realm improvements are indicated in the enclosed drawing and includes the following:

  • Repaving footways on Grafton Street and New Bond Street to provide new levelled access to the building;
  • Refreshment of carriageway resurfacing; and
  • Temporary removal and storage of all existing plaques, statues and bench while the highway work is carried out.

This survey closed on 19th March 2026. No responses were submitted during this period. As a result, we are proceeding with completing the highway design review and implementation of the highway works.

Timeline

Feasibility and Initial Design Reviews

March 2025 - November 2025
Reviewing design proposals put forward by the developer

Detailed Design review

January 2026 - April 2026
Review the detailed design proposals put forward by the developer

Construction

June 2026 - June / July 2026
Indicative dates for implementation of design proposals provided by developers.