Warwick Way Construction Updates - 28.04.2025
Phase 1 Warwick Way (between Upper Tachbrook Street and Wilton Road)Works are complete for Phase 1 with the exception of the installation of setts and chamfered to the loading bay outside Tesco.  
Warwick Way Town Centre Highways Scheme
Phase 1 Warwick Way (between Upper Tachbrook Street and Wilton Road)
Works are complete for Phase 1 with the exception of the installation of setts and chamfered to the loading bay outside Tesco. A temporary asphalt construction has been installed in this location to mitigate delays to materials. The works have now moved on to Phase 2 on Denbigh Street. To allow this to happen, Warwick Way has been made one-way westbound between its junctions with Upper Tachbrook Street and Belgrave Road with temporary road markings installed to inform road users.
Phase 2 Denbigh Street
Denbigh Street has been closed at its junction with Warwick Way. Works to construct the footway widening outside Uno Pronto to the Paradise Indian Restaurant will progress this week.
Further information:
If you have any questions while works are taking place on-site, please contact our Public Liaison Officer, Bob Burton. Bob can be reached at 07760 962103, although he may not be always on-site.
For more information on the scheme drawings and phasing plans, please visit here