Mill and Overlay Road Work
As part of the City’s ongoing pavement management program, Hubbard Construction will begin milling and repaving work throughout the City on select streets. All roads listed will remain open during construction, with traffic directed by crews on site.
Milling and repaving is a road rehabilitation process that restores worn asphalt by removing the top layer with a milling machine and replacing it with new asphalt. This process extends pavement life and fixes surface issues.
Work is scheduled to begin Monday, January 26, 2026, and continue through Thursday, February 26, 2026. Hours of operation will be 8:00 a.m. to 5:00 p.m. Provisions will be made to minimize inconvenience to businesses, residents, and routine services such as mail delivery. Drivers should follow all flaggers and detour signs for safety.
Digital message boards and information signage will be placed in the vicinity of the work in advance to alert motorists who travel the area.
For questions, please contact Streets & Drainage Superintendent Michael Campbell at (863) 291-5852 or mcampbell@mywinterhaven.com
Below is the list of streets scheduled to receive milling and repaving as part of this project.
All dates are subject to change due to potential weather impacts.
- 1/26/2026 13th Street SE From Lake Elbert Dr. To Lake Otis Dr.
- 1/26/2026 Lake Link Dr. SE From 14th Street SE To Lake Link Cir. SE
- 1/27/2026 Lake Link Cir. SE From Lake Link Dr. SE To Lake Link Cir. SE
- 1/28/2026 Lake Link Cir. SE From Lake Link Cir. SE To Oakridge Lane SE
- 1/28/2026 Lake Link Cir. SE From Lake Link Dr. SE To Dead End
- 1/29/2026 Oakridge Lane SE From Lake Link Dr. SE To Lake Link Cir. SE
- 1/29/2026 Peachtree Lane SE From Lake Link Cir. SE To Oakridge Lane SE
- 1/30/2026 Avenue D NE From Lake Elbert Dr. NE To 15th Street NE
- 1/30/2026 Drexel Avenue NE From Lake Elbert Dr. NE To 15th Street NE
- 1/30/2026 Avenue F NE From Lake Elbert Dr. NE To 15th Street NE
- 2/2/2026 Alleyway 1105 Lk. Elbert From Lake Elbert Dr. NE To Dead End
- 2/2/2026 8th Street NE From Lake Elbert Dr. NE To Avenue E NE
- 2/2/2026 Avenue D NE From 7th Street NE To End of Alleyway (Driveway)
- 2/3/2026 9th Court NE From Avenue O NE To Avenue M NE
- 2/3/2026 Edwin Street NE From Ware Avenue NE To Avenue U NE
- 2/4/2026 3rd Street NE From Avenue V NE To Dead End
- 2/4/2026 6th Street NW From W. MLK Blvd To Sears Avenue NW
- 2/4/2026 6th Street NW From Sears Avenue NW To Dead End
- 2/5/2026 Avenue L NW From US/17 North To 8th Street NW
- 2/6/2206 Alleyway 701 W. Central From 7th Street NW To Lake Howard NW
- 2/6/2026 Avenue F NW From 1st Street NW To 3rd Street NW
- 2/9/2206 Avenue B NE From 1st Street NE To 2nd Street NE
- 2/10/2206 2nd Street SE From E. Central Avenue To Avenue A SE
- 2/12/2026 Avenue E SE From 2nd Street SE To 6th Street SE
- 2/12/2026 Avenue D SE From 1st Street SE To 2nd Street SE
- 2/13/2026 Avenue E SE From 1st Street SE To 2nd Street SE
- 2/13/2026 Avenue F SE From 2nd Street SE To 4th Street SE
- 2/17/2026 Avenue F SE From 4th Street SE To 5th Street SE
- 2/17/2026 Avenue F SE From 5th Street SE To 6th Street SE
- 2/18/2026 Avenue F SE From 6th Street SE To Lake Otis Drive SE
- 2/19/2026 Avenue H SE From 1st Street SE To 6th Street SE
- 2/20/2026 Avenue I SE From 1st Street SE To 6th Street SE
- 2/23/2026 Avenue J SE From 1st Street SE To 4th Street SE
- 2/26/2026 Avenue O SE From 6th Street SE To 8th Street SE
- 2/26/2026 Avenue Q SW From Lake Shipp Dr. SW To Recker Hwy SW
- 2/25/2026 24th Court SW From 24th Street SW To 24th Street SW
- 2/26/2026 Lake Marianna Dr. NW From Osprey Way NW To Asphalt Cut Point
- 2/26/2026 Old Lucerne Park Road (2) areas for asphalt repair