Resurfacing improvements will take place on S Nebo Road from the State Road 32 intersection south to W Cornbread Road to enhance driving conditions along this local connector route.

S Nebo Road Improvement Project

Project Overview

The Town of Yorktown will complete resurfacing improvements along S Nebo Road, beginning at the State Road 32 intersection and extending south to W Cornbread Road.

S Nebo Road serves as an important connection for local residents and surrounding rural areas. Resurfacing this corridor will improve travel conditions while protecting the roadway from long-term deterioration.

Project Limits

Start: State Road 32 intersection (State Right of Way)
End: W Cornbread Road

Construction will begin at the State Right of Way (SROW) along State Road 32 and extend south along S Nebo Road.

Funding

The S Nebo Road project is included in Yorktown’s 2026 road improvement program, totaling $690,419.68.

Half of the project cost is funded through the INDOT Community Crossings Matching Grant Program, allowing the Town to significantly expand roadway improvements through a state and local partnership.

Yorktown remains committed to pursuing these competitive infrastructure grants each year.

What Residents Can Expect

Residents may see temporary traffic adjustments or construction activity during resurfacing operations. Additional updates regarding project timing and construction phases will be shared as work approaches.

Map of Construction Area

Timeline

Project Start:

June 9, 2026
Traffic control and milling begin.

Road Preparation:

June 9–June 11, 2026
Pavement repairs and base work.

Paving

June 12, 2026
Final asphalt surface installed.