5/12/24 Update and Lookahead
Neighborhood 2 & 6

5/12/24 Update and Lookahead

Update on project with timeline

Maple Street (south side):
On Going: Concrete curb and gutter formwork, reinforcement install, and concrete placements.

Broadway:
Completed: Last week we completed the backfilling of curbs with topsoil.
On Going: The roadway, curbs and gutters, and lead walks were all swept. Striping and modifying the signage on Broadway at Malone. Sod installation is pending weather impacts.

Hillcrest:
Completed: Concrete removals
On Going: Subgrade grading, Utility clearance confirmation and conflict identification.

Crescent (Ector to Hillcrest):
Completed: Survey of curb and gutter & saw cutting the outer edge of asphalt for C&G clearance.
OnGoing: Curb and gutter formwork with reinforcement.

Thomas/Crescent/Linden:
On Going: Installation of the 8" sewer main with new lateral connections working south on Thomas from Cresent. 8" sanitary sewer will terminate near Linden, with remaining laterals following. Efforts will shift north to Thomas/Emery, starting with manholes and bypass pumping.

For more information - follow the SUNDT Project Update Site at:

Neighborhoods 2 & 6 - Denton Utilities Improvements by Sundt (sundtdenton.com)