Neighborhood 2 & 6

The Neighborhood 2 & 6 reconstruction is an approximately $80 million project funded by the 2019 Street Rehabilitation Bond Program. Covering about 120 road segments, this project is part of a multi‑phase effort to rebuild streets that have reached the end of their useful life.

Maps are available showing all streets included in the Neighborhood 2 & 6 project, along with the phase breakdown (Packages 1, 2, and 3). Reconstruction work will include new curbs and gutters, asphalt or concrete roadway surfaces, and upgrades to select water and wastewater facilities. Some locations will also receive sidewalk and street lighting upgrades.

Project Timeline Q4 2022 - Q4 2026*

*Estimated project timelines may change due to weather, contractor scheduling, among other factors and will be updated as needed.

Additional updates provided by Sundt Construction can be found here.

Map of project area

Stay Informed

Get notified on upcoming engagements and the latest project related news.

Photograph of Megan Davidson
Megan Davidson
Construction Projects Manager
Photograph of Scott Fettig
Scott Fettig
Senior Project Manager

Project Updates

42 items

Neighborhood 2&6 May 2026 Construction Update

Biweekly Neighborhood 2&6 update for streets with active construction.

View Update

Neighborhood 2&6 April 2026 Construction Update - 3

Biweekly Neighborhood 2&6 update for streets with active construction.

View Update

Neighborhood 2&6 April 2026 Construction Update - 2

Biweekly Neighborhood 2&6 update for streets with active construction.

View Update

Neighborhood 2&6 April 2026 Construction Update

Biweekly Neighborhood 2&6 update for streets with active construction.

View Update

March 2026 Construction Update

March 2026 Construction Update

View Update

February 2026 Construction Update - 2

February 2026 Construction Update - 2

View Update

February 2026 Construction Update

February 2026 Construction Update

View Update

January 2026 Construction Update - 2

January 2026 Construction Update - 2

View Update

January 2026 Construction Update

January 2026 Construction Update

View Update

December 2025 Construction Update

December 2025 Construction Update

View Update

November 2025 Construction Update

November 2025 Construction Update

View Update

October 2025 Construction Update - 2

Work Packages 2 and 3 are in construction with anticipated completion Q4 2026.

View Update

October 2025 Construction Update

Work Packages 2 and 3 are in construction with anticipated completion Q4 2026.

View Update

September 2025 Construction Update - 2

Work Packages 2 and 3 are in construction with anticipated completion Q4 2026.

View Update

September 2025 Construction Update

Construction update for project

View Update

August 2025 Construction Update - 2

All project update details and information

View Update

August 2025 Construction Update

Update on all construction for project

View Update

12/12/24 New Traffic Pattern - Avenue C Is Opening Up Today!

Ongoing work and schedules around UNT

View Update

2024 11-18 UNT Area Update

Construction Update for this week

View Update

Look Ahead Near UNT

Below is a long-lead lookahead for Future Construction Impacts Near UNT

View Update

11/12/2024 Look Ahead Update

On-going construction update

View Update

Look-Ahead Update 8/24/24

Updated project details and timeline

View Update

6/28/24 Update and Lookahead

Construction crews have been working HARD in this HEAT. They will be observing the 4th of July and returning back to work Monday July 8. That's right, everyone gets a Construction-Free Long Weekend!

View Update

6/10/24 Update and Lookahead

THE LIST IS GROWING!!! SUNDT Construction and their Subs are making great progress

View Update

6/4/24 Update and Lookahead

Below is an update on what has taken place last week and what's planned this week (weather permitting)

View Update

Work Package #2 is starting SOON

Virtual Community Meeting is scheduled for May 30, 2024 at 6:00 pm.

View Update

5/12/24 Update and Lookahead

Update on project with timeline

View Update

Traffic Control Update - Crescent - Linden - Thomas

TRAFFIC CONTROL UPDATE - CRESCENT - LINDEN - THOMAS

View Update

4/22/2024 Update and Lookahead

An update on project and timeline

View Update

4/5/2024 Update & Lookahead

An update and lookahead for full project

View Update

3/29/2024 Update

Good Friday is wrapping up as is good progress on the Neighborhood 2&6 project street sections.

View Update

3/22/2024 Update

Update of all construction

View Update

February Update

Neighborhood 2 & 6 project is currently in the design and construction phases.

View Update

January Update

Neighborhood 2 & 6 project is currently in the planning and design phase.

View Update

December Update for Neighborhood 2 & 6

Neighborhood 2 & 6 project is currently in the planning and design phase.

View Update

November Update for Neighborhood 6

Neighborhood 6 project is currently in the planning and design phase.

View Update

September Update for Neighborhood 6

Neighborhood 6 project is currently in the planning and design phase.

View Update

Update for Neighborhood 6 Project

Neighborhood 6 project is currently in the planning and design phase.

View Update

Update for Neighborhood 6 Project

Neighborhood 6 project is currently in the planning and design phase.

View Update

Project Update for Neighborhood 6

Neighborhood 6 project is currently in the planning and design phase.

View Update

Neighborhood 6 Project Update

Neighborhood 6 project is currently in the planning and design phase.

View Update

2019 Bond Neighborhood 6 Update

Neighborhood 6 project is currently in the planning and design phase.

View Update