Neighborhood 2 & 6
The Neighborhood 2 & 6 reconstruction is an approximately $80 million project funded by the 2019 Street Rehabilitation Bond Program. Covering about 120 road segments, this project is part of a multi‑phase effort to rebuild streets that have reached the end of their useful life.
Maps are available showing all streets included in the Neighborhood 2 & 6 project, along with the phase breakdown (Packages 1, 2, and 3). Reconstruction work will include new curbs and gutters, asphalt or concrete roadway surfaces, and upgrades to select water and wastewater facilities. Some locations will also receive sidewalk and street lighting upgrades.
Project Timeline Q4 2022 - Q4 2026*
*Estimated project timelines may change due to weather, contractor scheduling, among other factors and will be updated as needed.
Additional updates provided by Sundt Construction can be found here.
Stay Informed
Get notified on upcoming engagements and the latest project related news.


Project Updates
Neighborhood 2&6 May 2026 Construction Update
Biweekly Neighborhood 2&6 update for streets with active construction.
Neighborhood 2&6 April 2026 Construction Update - 3
Biweekly Neighborhood 2&6 update for streets with active construction.
Neighborhood 2&6 April 2026 Construction Update - 2
Biweekly Neighborhood 2&6 update for streets with active construction.
Neighborhood 2&6 April 2026 Construction Update
Biweekly Neighborhood 2&6 update for streets with active construction.
March 2026 Construction Update
March 2026 Construction Update
February 2026 Construction Update - 2
February 2026 Construction Update - 2
February 2026 Construction Update
February 2026 Construction Update
January 2026 Construction Update - 2
January 2026 Construction Update - 2
January 2026 Construction Update
January 2026 Construction Update
December 2025 Construction Update
December 2025 Construction Update
November 2025 Construction Update
November 2025 Construction Update
October 2025 Construction Update - 2
Work Packages 2 and 3 are in construction with anticipated completion Q4 2026.
October 2025 Construction Update
Work Packages 2 and 3 are in construction with anticipated completion Q4 2026.
September 2025 Construction Update - 2
Work Packages 2 and 3 are in construction with anticipated completion Q4 2026.
September 2025 Construction Update
Construction update for project
August 2025 Construction Update - 2
All project update details and information
August 2025 Construction Update
Update on all construction for project
12/12/24 New Traffic Pattern - Avenue C Is Opening Up Today!
Ongoing work and schedules around UNT
2024 11-18 UNT Area Update
Construction Update for this week
Look Ahead Near UNT
Below is a long-lead lookahead for Future Construction Impacts Near UNT
11/12/2024 Look Ahead Update
On-going construction update
Look-Ahead Update 8/24/24
Updated project details and timeline
6/28/24 Update and Lookahead
Construction crews have been working HARD in this HEAT. They will be observing the 4th of July and returning back to work Monday July 8. That's right, everyone gets a Construction-Free Long Weekend!
6/10/24 Update and Lookahead
THE LIST IS GROWING!!! SUNDT Construction and their Subs are making great progress
6/4/24 Update and Lookahead
Below is an update on what has taken place last week and what's planned this week (weather permitting)
Work Package #2 is starting SOON
Virtual Community Meeting is scheduled for May 30, 2024 at 6:00 pm.
5/12/24 Update and Lookahead
Update on project with timeline
Traffic Control Update - Crescent - Linden - Thomas
TRAFFIC CONTROL UPDATE - CRESCENT - LINDEN - THOMAS
4/22/2024 Update and Lookahead
An update on project and timeline
4/5/2024 Update & Lookahead
An update and lookahead for full project
3/29/2024 Update
Good Friday is wrapping up as is good progress on the Neighborhood 2&6 project street sections.
3/22/2024 Update
Update of all construction
February Update
Neighborhood 2 & 6 project is currently in the design and construction phases.
January Update
Neighborhood 2 & 6 project is currently in the planning and design phase.
December Update for Neighborhood 2 & 6
Neighborhood 2 & 6 project is currently in the planning and design phase.
November Update for Neighborhood 6
Neighborhood 6 project is currently in the planning and design phase.
September Update for Neighborhood 6
Neighborhood 6 project is currently in the planning and design phase.
Update for Neighborhood 6 Project
Neighborhood 6 project is currently in the planning and design phase.
Update for Neighborhood 6 Project
Neighborhood 6 project is currently in the planning and design phase.
Project Update for Neighborhood 6
Neighborhood 6 project is currently in the planning and design phase.
Neighborhood 6 Project Update
Neighborhood 6 project is currently in the planning and design phase.
2019 Bond Neighborhood 6 Update
Neighborhood 6 project is currently in the planning and design phase.