Construction for Package 1 (GMP1) has completed.
Packages 2 and 3 are in construction with anticipated completion Q4 2026
Streets with active construction:
- Aileen - (Panhandle to Cordell) Had significant delays due to weather and Atmos conflicts but nearing completion.
- Ave. D - (Chestnut to Mulberry)
- Chestnut - (Ave. D to Ave. C)
- Congress - (Ponder St. to Carroll)
- Congress West - (Malone to Bryan)
- Crescent East - (Carroll to Bolivar) Asphalt completion week of Aug.11
- Crescent West - (Aileen to Malone)
- Denton St. - (Hickory to Congress)
- Egan St. - (Carroll to Bolivar)
- Mulberry St. - (Welch to Bernard)
- Ponder Ave. - (Oak to Panhandle)
- Sunset St. 1 - (University to Carroll)
- Sunset St. 2 - (Carroll to Bolivar)
- Union Circle - (Prairie to Chestnut)
- Welch St. - (Eagle to Hickory) Constructed in segments. Completed segments are Highland to Eagle and Prairie to Sycamore
- Scripture St. - (Jagoe to Ponder) *Delayed due to Atmos conflicts. Atmos conflicts are scheduled to be completed 9/1/25 at which point roadway construction will resume