
Work Packages 2 and 3 are in construction with anticipated completion Q4 2026.
Streets with active construction:
Utilities:
- Bernard North (Chestnut / Hickory) – Continue installing 8" water main on line A followed by chlorination and tie-ins.
Earthwork/Flatwork:
- Alice (Panhandle / Crescent) – Curb and gutter, driveways, sidewalks, and miscellaneous concrete.
- Denton St. (Hickory / Congress E) – ATMOS delay.
- Egan (East - Anna / Bolivar) – Pending placement of sod.
- Emery and Fulton – Continue driveways and miscellaneous concrete work.
- Normal (Scripture / Oak) – Pending placement of sod and striping.
- Panhandle (Fulton / Denton) – Continue sidewalks and miscellanous concrete work.
- Parkway (Denton / Carroll) – Begin curb, gutter, driveways, and miscellaneous concrete work.
- Ponder (Grace Temple / Oak) – Continue curb, gutter, driveways, and miscellaneous concrete.
- Prairie – Concrete sidewalk at Bernard.
- Scripture West (Malone / Bryan) – Continue rough grading followed by lime treated subgrade.
- Scripture East (Bryan / Ponder) – Continue rough grading followed by lime treated subgrade.
- Sunset (Carroll / Bolivar) – Continue driveways and miscellaneous concrete followed by backfilling and sod.
Stay Informed
Get notified on upcoming engagements and the latest project related news.