6/4/24 Update and Lookahead
Neighborhood 2 & 6

6/4/24 Update and Lookahead

Below is an update on what has taken place last week and what's planned this week (weather permitting)

We hope you have been safe. Winds and Rains have definitely been an issue for construction - and continues to be! Thank you for your patience and understanding! Below is an update on what has taken place last week and what's planned this week (weather permitting)



Central:

LAST Week: Utility Locates were completed. Survey is working on R.O.W. staking and work limits.

THIS Week: Traffic control measures will be on the road Monday to be utilized for the road shutdown to begin road reconstruction starting with potholing.





Welch (Eagle to Highland):

LAST Week: Utility Locates were completed. Survey is working on providing staking.

THIS Week: Traffic control measures will be on the road Monday to be utilized for the road shutdown to begin utility work.





Ave. D & Chestnut

LAST Week: Locates were completed. Survey is working on providing staking.

THIS Week: Traffic control measures will be on the road Monday to be utilized for the road shutdown to begin utility work Tuesday.





Maple Street (south side):

LAST Week: The continuance of concrete curb and gutter formwork, reinforcement install, and concrete placements occurred in limited amounts this week due to weather.

THIS Week: will the added drainage adjacent to the intersection of Ave B and continue concrete placements for sidewalks.





Broadway:

LAST Week: The majority of the sod was installed at BOC adjoining existing residential lawns.

THIS Week: Plan to complete the sod and start the Sundt punch process.





Hillcrest:

LAST Week: The lime mixing process, compaction, and lime depth testing completed with fine grading started.

THIS Week: Complete the grading and seal the roadway with an emulsion coat prior to Texas Materials placing asphalt Friday into the following week.





Crescent (Crescent to Panhandle):

LAST Week: Completed potholing of existing utility crossings at the Back of Curbs. Saw cutting for concrete removals was completed.

THIS Week: Start the milling of asphalt. After several days of milling, will begin the concrete removal process.





Thomas (Emery to Crescent):

LAST Week: Progress made on the sewer main and laterals moving south from Emery.

THIS Week: Will continue south with both the main and laterals.





Crescent (West of Thomas) and Linden:

THIS Week: Will be completing potholing and saw cutting in preparation for milling to follow.







For more information - follow the SUNDT Project Update Site at:

Neighborhoods 2 & 6 - Denton Utilities Improvements by Sundt (sundtdenton.com)

Stay Informed

Get notified on upcoming engagements and the latest project related news.