Below is a long-lead lookahead for Future Construction Impacts Near UNT
We know the impacts of construction are challenging. Below is a long-lead lookahead for Future Construction Impacts Near UNT. The City of Denton, DCTA, and UNT are coordinating work in/around UNT to minimize impacts to work near special events such as commencements and semester move-ins. We are also making our best efforts to maximize work during winter/summer breaks. We appreciate your support for this huge project!!
Spring 2025
Avenue C Roadway
Eagle to Highland: To end by 12/12/24 latest
Welch Roadway
Prairie to Chestnut: 12/18/24 – 3/21/25
Chestnut to Mulberry: 3/31/25 – 06/16/25
Prairie Street Utilities
Welch to Bernard: 11/18/24 – 02/24/25
Prairie Street Roadway Work
Bernard to Welch: 02/25/25 – 06/11/25
Mulberry Utilities
Welch to Bernard: 02/25/25 – 05/13/25
Mulberry Roadway
Welch to Bernard: 05/14/25 – 08/06/25
Bernard South Roadway (Fannin to Lindsey)
Lindsey to Fannin: 12/31/24 – 06/23/25
Avenue A Utilities
Ave A/Maple Intersection: 01/24/25 – 02/28/25
Summer 2025
Chestnut Roadway
Ave C to Ave D: 5/16/25 – 8/25/25
Ave. D Roadway
Chestnut to Mulberry (05/13/25 – 08/12/25
Welch Roadway Work
Chestnut to Mulberry: 3/31/25 – 06/16/25
Mulberry to Hickory: 07/25/24 – 09/22/25
Prairie Street Roadway Work
02/25/25 – 06/11/25
Union Circle Utilities
South (Prairie): 5/14/25-7/11/25
Union Circle Roadway
All: 7/11/25 – 10/02/25
Mulberry Roadway
Welch to Bernard: 4/23/25-7/22/25
Welch Roadway Work
Mulberry to Hickory: 07/25/25 – 09/22/25
Fall 2025
Chestnut Roadway
Ave C to Ave D: 5/16/25 – 8/25/25
Welch Roadway Work
Eagle to Highland: 08/22/25 – 11/17/25
Highland to Prairie: 10/25 – 01/26/26
Union Circle Utilities
South (Prairie): 5/14/25-7/11/25
West: 5/14/25-7/11/25
North (Chestnut): 5/14/25-7/11/25
Union Circle Roadway
South (Prairie): 7/11/25 – 10/02/25
West: 7/11/25 – 10/02/25
North (Chestnut): 7/11/25 – 10/02/25
Welch Roadway Work
Mulberry to Hickory: 07/25/25 – 09/22/25
Spring 2026
Bernard North Utilities
Hickory to Chestnut: 01/12/26 – 02/27/26
Bernard North Roadway
Hickory to Chestnut: 02/27/26 – 06/09/26
Avenue A Utilities
Eagle to Maple: 2/25/26-4/2/26
Ave A/Maple Intersection: 4/3/26-7/13/26
Summer 2026
Bernard North Roadway
Hickory to Chestnut: 4/3/26-7/8/26