Neighborhood 2 & 6
October 2025 Construction Update
Work Packages 2 and 3 are in construction with anticipated completion Q4 2026.
Work Packages 2 and 3 are in construction with anticipated completion Q4 2026.
Streets with active construction:
Utilities:
- Normal (W. Oak / Scripture) – Continue water main and lateral.
- Ponder (W. Oak / Panhandle) – Chlorination testing.
- Alice (Panhandle / Crescent) – Backfill bore operation followed by installation of sewer line.
Electrical:
- Aileen (Panhandle / Cordell) – Light conduit and boxes continued.
- Carlton (Aileen / Gober) – Light conduit and boxes to begin.
Earthwork/Flatwork:
- Amarillo (Haynes / Congress E) – Demo saw cutting followed by asphalt and concrete removals.
- Avenue G (Prairie / Louise) – Pending asphalt infill.
- Carlton (Aileen / Gober) – Backfill, sod, striping, and signage.
- Congress E (Denton / Carroll) – Striping and signage.
- Cordell (Crescent / Fulton) – Continuing curb, gutter, and driveways.
- Cordell (Fulton / Alice) – Fine grading follow by 1st lift of asphalt and flatwork activities.
- Denton St. (Hickory / Congress E) – Curb, gutter, driveways, and miscellaneous concrete work.
- Egan (West) – First lift of asphalt followed by curb, gutter, and driveways.
- Mounts (Haynes / Congress E) – Curb, gutter, driveways, and miscellaneous concrete work.
- Ponder (Scripture / Grace Temple) – Continuing concrete removals followed by rough grading and lime mixing.
- Scripture (Jagoe / Ponder) – ATMOS re-design.
- Sunset North (University / Carroll) – Concrete driveways and miscellaneous concrete work.
- Union Circle - open to traffic.
- Welch (Highland / Prairie) – Curb, gutter, driveways, and miscellaneous concrete work.
- Welch (Chestnut Intersections) – Striping
- Welch (Mulberry / Hickory) – Asphalt and concrete removals to being followed by rough grading.