Work Packages 2 and 3 are in construction with anticipated completion Q4 2026.
Streets with active construction:
Utilities:
- Alice (Panhandle / Crescent) – Tie-ins have been competed.
- Ponder / Scripture – Continue installing multiple inlets.
- Bernard North (Chestnut / Hickory) – Started installing 8" water main on line B followed by chlorination and tie-ins.
Earthwork/Flatwork:
- Alice (Panhandle / Crescent) – Demo and asphalt removals to begin followed by rough grading.
- Denton St. (Hickory / Congress E) – ATMOS delay.
- Egan (Anna / Bolivar) – Pending placement of sod.
- Emery and Fulton – Continue curb and gutter followed by driveways and miscellaneous concrete work.
- Normal (Scripture / Oak) – Pending placement of sod and striping.
- Panhandle (Fulton / Denton) – Continue curb and gutter followed by driveways and miscellanous concrete work.
- Parkway (Denton / Carroll) – Concrete removals to begin followed by rough grading.
- Ponder (Panhandle / Egan) – Continue installing curb and gutter followed by backfilling and asphalt.
- Ponder (Egan / Scripture) – 2nd and final lift of asphalt to be placed followed by striping and signage.
- Ponder (Scripture / Grace Temple) – 2nd and final lift of asphalt to be placed followed by striping and signage.
- Scripture (Jagoe / Ponder) – ATMOS delay followed by re-installing traffic control.
- Sunset (Carroll / Bolivar) – Curb and gutter to begin.