February 2026 Construction Update - 2
Neighborhood 2 & 6

February 2026 Construction Update - 2

February 2026 Construction Update - 2

Work Packages 2 and 3 are in construction with anticipated completion Q4 2026.

Streets with active construction:

Utilities:

  • Alice (Panhandle / Crescent) – Tie-ins have been competed.
  • Ponder / Scripture – Continue installing multiple inlets.
  • Bernard North (Chestnut / Hickory) – Started installing 8" water main on line B followed by chlorination and tie-ins.

Earthwork/Flatwork:

  • Alice (Panhandle / Crescent) – Demo and asphalt removals to begin followed by rough grading.
  • Denton St. (Hickory / Congress E) – ATMOS delay.
  • Egan (Anna / Bolivar) – Pending placement of sod.
  • Emery and Fulton – Continue curb and gutter followed by driveways and miscellaneous concrete work.
  • Normal (Scripture / Oak) – Pending placement of sod and striping.
  • Panhandle (Fulton / Denton) – Continue curb and gutter followed by driveways and miscellanous concrete work.
  • Parkway (Denton / Carroll) – Concrete removals to begin followed by rough grading.
  • Ponder (Panhandle / Egan) – Continue installing curb and gutter followed by backfilling and asphalt.
  • Ponder (Egan / Scripture) – 2nd and final lift of asphalt to be placed followed by striping and signage.
  • Ponder (Scripture / Grace Temple) – 2nd and final lift of asphalt to be placed followed by striping and signage.
  • Scripture (Jagoe / Ponder) – ATMOS delay followed by re-installing traffic control.
  • Sunset (Carroll / Bolivar) – Curb and gutter to begin.