Work Packages 2 and 3 are in construction with anticipated completion Q4 2026.
Streets with active construction:
Utilities:
- Amarillo (Haynes / Congress E) – Continue waterlines and laterals.
- Egan (Carroll / Bolivar) – Pressure test and chlorination with tie-ins to follow.
- Normal (W. Oak / Scripture) – Installing 18" RCP and Junction Boxes followed by water line.
- Ponder (W. Oak / Panhandle) – Continue waterlines and laterals.
- Alice (Panhandle / Crescent) - Boring operations to being.
Electrical:
- Aileen (Panhandle / Cordell) - Light conduit and boxes to begin.
- Union Circle North - Installing conduit boxes.
Earthwork/Flatwork:
- Aileen (Panhandle / Cordell) – Pending striping and signage.
- Avenue G (Prairie / Louise) – Completed asphalt with TCP pick-up on 9/5.
- Carlton (Aileen / Gober) – Asphalt completed and continuing placement of curb and gutter.
- Congress E (Ponder / Denton) – Continuing curb, gutter, and driveways.
- Congress E (Denton / Carroll) – 1st lift of asphalt scheduled with curb and gutter to follow.
- Congress W (Malone / Bryan) – Asphalt completed with striping, signage, and TCP pick-up to follow.
- Cordell (Fulton / Crescent) – 1st lift of asphalt completed.
- Crescent (Carroll / Bolivar) – Continuing concrete driveway and miscellaneous concrete work.
- Denton St. (Hickory / Congress E) – Rough grading completed with cem-line scheduled.
- Mounts (Haynes / Congress E) – Demo completed and mixing schedule with mellow and remixing to follow.
- Mulberry (Welch / Bernard N) – Backfill completed and pending sod.
- Scripture (Jagoe / Ponder) – ATMOS re-design.
- Sunset South (University / Carroll) – Traffic switch completed with removals and earthwork started.
- Union Circle North - Continuing concrete work with backfiling to follow.
- Welch (Sycamore / Mulberry) – Throats and tops to be completed with backfill to follow.