Work Packages 2 and 3 are in construction with anticipated completion Q4 2026.
Streets with active construction:
Utilities:
- Alice (Panhandle / Crescent) – Tie-ins have been scheduled.
- Parkway (Denton / Carroll) – Continue water main and laterals followed by chlorination testing. Carroll Blvd will have a 2-lane closure to install a sanitary sewer manhole.
- Ponder / Scripture – Continue installing multiple inlets.
- Bernard North (Chestnut / Hickory) – Traffic control placed and installation of water main has begun.
Earthwork/Flatwork:
- Ave A / Collins – Pending completion of decorative concrete.
- Denton St. (Hickory / Congress E) – ATMOS delay.
- Egan (Anna / Bolivar) – Final lift of asphalt is scheduled with striping, signage, and removal of traffic control to follow.
- Emery and Fulton – Curb and gutter to begin.
- Normal (Scripture / Oak) – Continue curb, gutter, sidewalks, and driveways followed by backfilling and sod.
- Panhandle (Fulton / Denton) – Continue fine grading followed by 1st lift of asphalt and concrete work.
- Parkway (Denton / Carroll) – 48-hour notices to be issued followed by traffic control.
- Ponder (Panhandle / Egan) – Continue installing reinforced concrete pipe (RCP) followed by asphalt.
- Ponder (Egan / Scripture) – Continue driveways, inlets, and miscellaneous concrete followed by backfilling and sod.
- Ponder (Scripture / Grace Temple) – Continue curb, gutter, sidewalks, driveways, and inlets.
- Ponder (Grace Temple / Oak) – Continue fine grading followed by asphalt.
- Ponder at Scripture – ATMOS delay.
- Prairie (Welch / Bernard) – Continue curb, gutter, sidewalks, and backfilling followed by sod.
- Scripture (Jagoe / Ponder) – ATMOS delay followed by re-installing traffic control.
- Sunset (Carroll / Bolivar) – Continue rough grading followed by stabilization of subgrade and fine grading.
- Welch – Pending completion of decorative concrete.