Neighborhood 2&6 Streets with Active Construction

Neighborhood 2 & 6

Work Packages 2 and 3 are in construction with anticipated completion Q4 2026.

Streets with active construction:

Bernard North (North) – Pending first lift of asphalt.
Bernard at Sycamore – Installation of water line and storm drain.
Bernard North (South) – Continue installation of curb, gutter, and driveways.
Scripture Street – Pending striping and signage followed by removal of traffic control.