Work Packages 2 and 3 are in construction with anticipated completion Q4 2026.
Streets with active construction:
Utilities:
- Normal (W. Oak / Scripture) – Continue installing reinforced concrete pipe.
- Alice (Panhandle / Crescent) – Continue installation of sewer lines followed by water mains and laterals.
- Parkway (Denton / Carroll) – Continue boring water line across Carroll and sewer main folled by water lines.
Earthwork/Flatwork:
- Amarillo (Haynes / Congress E) – Curb, gutter, driveways, and miscellaneous concrete.
- Cordell (Coit / Fulton) – Sod, striping, singange, and traffic control removal to be completed.
- Denton St. (Hickory / Congress E) – ATMOS re-design.
- Egan (West - Carroll / Anna) - Continue curb, gutter, and miscellaneous concrete work followed by sod and final lift of asphalt.
- Egan (East - Anna / Bolivar) - Traffic control placement followed by removals.
- Emery & Fulton - Begin curb and gutter.
- Mounts (Haynes / Congress E) – Continue curb, gutter, driveways, and miscellaneous concrete work followed by sod.
- Normal (Scripture / Oak) - Traffic control placed followed by removals.
- Ponder (Scripture / Grace Temple) – Being curb and gutter.
- Ponder (Egan / Scripture - Lime followed by fine grading and 1st lift of asphalt.
- Scripture (Jagoe / Ponder) – ATMOS re-design.
- Sunset (University / Alice) – Parking lot asphalt to be placed.
- Welch (Highland / Prairie) – 2nd lift of asphalt compete followed by 3rd lift, striping, signage, and traffic control removal.
- Welch (Mulberry / Hickory) – Continue curb, gutter, driveways, and miscellaneous concrete work followed by sod and final lift of asphalt.