Fire House #5 and #6

Construction Progress

Fire Station #5


ACHIEVEMENTS:  Building demoed  Coordination with Bonnie Brae project connections NEXT STEPS:  Prep site for underground work  Install Underground Sanitary Sewer  Drill piers


Fire Station #6 ACHIEVEMENTS:  Concrete Pours Completed  Began CMU Wall Installation  Steel Beams and Columns has begun


NEXT STEPS:  Complete Steel Work  Begin Framing working  Install Roof decking and roof system