Visit Denton, TX Homepage
Areial Shot of Fire Station 6 construction site

Fire House #5 and #6

Fire Station #5


Location & Purpose: A complete reconstruction of the existing facility to better serve the expanding northwest portion of Denton.
Key Features:
Four (4) Apparatus Bays
Strategic Traffic Engineering: The site layout features optimized logistics and a specialized egress orientation directly onto Windsor Drive. This minimizes response delays and traffic congestion conflicts
Enhanced Crew Quarters: Modernized bunk rooms, a dedicated physical training room, and an open-concept kitchen/living area designed to support health and wellness.

Fire Station #6 (New District Facility)

Location & Purpose: A brand-new facility engineered to address surging call volumes and reduce emergency response times in its designated service district.
Key Features:
Three (3) Apparatus Bays
Expanded Personnel Capacity: Fully equipped living quarters designed to support ten (10) personnel on a 24-hour shift rotation.
Dedicated Officer Spaces: Private quarters and administrative offices for two (2) officers to oversee shift management

FS #6

FS #6

Stay Informed

Get notified on upcoming engagements and the latest project related news.

photo of gio
Gio Pineiro-Villalba, PhD, PMP
Construction Projects Manager

Project Updates

23 items

Construction Progress

Fire Station #6:

ACHIEVEMENTS:
 Steel work completed over the Bays and House
 Framers mobilized
 Building Dry-In
 Box walk with the City team

Posted:
View Update

Construction Progress

Posted:
View Update

Station 5 & 6 Achievements and Next Steps

Posted:
View Update

Steel Work Completed over the Bays and House for Station 6 along with more construction updates for stations 5 & 6!

Fire Station #6:
Steel work completed over the Bays and House
Complete Steel Work – Facility Side
Install Roof decking and roof system

Fire Station #5
Pouring Grade Beams
Slab Pour

Posted:
View Update

Fire Station 5 & 6 updates, achievements and next steps in the construction process

Posted:
View Update

Construction Progress

Construction Progress

Posted:
View Update

Construction Progress

Update provided for First Station 5 and Fire Station 6

Posted:
View Update

Construction Progress

New update

Posted:
View Update

Construction Progress

Achievements and next steps

Posted:
View Update

Design/Procurement Phase

Achievements and next steps

Posted:
View Update

Design/Procurement Phase

New Updates

Posted:
View Update

Design/Procurement Phase

Achievements and updates

Posted:
View Update

Design/Procurement Phase

Achievements and next steps

Posted:
View Update

Design/Procurement Phase

New Update

Posted:
View Update

Design/Procurement Phase

Achievements and next steps

Posted:
View Update

Design/Procurement Phase

New Update

Posted:
View Update

Design Phase

Achievements

Posted:
View Update

Design Phase

New Update

Posted:
View Update

Design Phase

Achievements and next steps

Posted:
View Update

Design Phase

New Updates

Posted:
View Update

Design Phase

Achievements and next steps

Posted:
View Update

Design Phase

Achievements and next steps

Posted:
View Update

Schematic Design Phase

Achievements

Posted:
View Update