ACHIEVEMENTS:
GMP Creation
GMP Converted to Stipulated Lump Sum Contract
ILA Pflugerville/Denton for Temp Trailer Executed
All Permitting Documents Submitted to City of Denton for Both Temp and Permanent
NEXT STEPS:
Stipulated Sum GMP Negotiations
Finalized GMP to City 3-JUL
GMP to CC 15-JUL or 22-JUL
SWPPP Permitting to Compete
Finalize all Permitting
Temporary Fire Station 5 Trailer Delivery 3-JUL
NTP 16 or 23 JUL for Temp Fire 5 and Fire 6