Denton, TX
Construction Progress
Fire House #5 and #6

Construction Progress

Construction Progress

ACHIEVEMENTS: *Fire Station #6

  • 100% Piers Complete
  • Grade Beams (Apparatus Bay) Complete
  • Grade Beams (Operations Side) Formed
  • South Storm Sewer 50%
  • Pour Grade Beams (Operations Side)
  • Start Storm Sewer Install
  • Excavate & Install Water Line
  • Excavate & Install Storm Line
  • Excavate & Install Gas Line
  • Excavate & Install Power Line
  • Underground MEP (Bay and Ops)
  • Civil work for paving
  • Concrete Pours Completed
  • Began CMU Wall Installation

**ACHIEVEMENTS:**Fire Station #5

  • Sprung Structure Grading
  • Temp Station Submittals
  • Domestic Water Line
  • UG Power Line
  • Sanitary Sewer Line
  • Fire 5 Erosion Control/Watershed Inspection
  • Temp Station Flex base
  • Sprung Foundation
  • Install Sprung Structure
  • Install OH Doors
  • Install Electric Underground Feed from Transformer
  • Install Sanitary Temp
  • Install Concrete Pads for Generator and Riser Room
  • RPZ installed
  • Move into Temp Structure

**NEXT STEPS: ** FS#5 & FS#6

  • Demo existing station
  • Prep site for underground work
  • Complete CMU Load Bearing Walls
  • Begin Steel Erection

FS #6

Stay Informed

Get notified on upcoming engagements and the latest project related news.