ACHIEVEMENTS: *Fire Station #6
- 100% Piers Complete
- Grade Beams (Apparatus Bay) Complete
- Grade Beams (Operations Side) Formed
- South Storm Sewer 50%
- Pour Grade Beams (Operations Side)
- Start Storm Sewer Install
- Excavate & Install Water Line
- Excavate & Install Storm Line
- Excavate & Install Gas Line
- Excavate & Install Power Line
- Underground MEP (Bay and Ops)
- Civil work for paving
- Concrete Pours Completed
- Began CMU Wall Installation
**ACHIEVEMENTS:**Fire Station #5
- Sprung Structure Grading
- Temp Station Submittals
- Domestic Water Line
- UG Power Line
- Sanitary Sewer Line
- Fire 5 Erosion Control/Watershed Inspection
- Temp Station Flex base
- Sprung Foundation
- Install Sprung Structure
- Install OH Doors
- Install Electric Underground Feed from Transformer
- Install Sanitary Temp
- Install Concrete Pads for Generator and Riser Room
- RPZ installed
- Move into Temp Structure
**NEXT STEPS: ** FS#5 & FS#6
- Demo existing station
- Prep site for underground work
- Complete CMU Load Bearing Walls
- Begin Steel Erection