ACHIEVEMENTS:
50% Construction Documents (City Review)
100% Extreme Modular Building Design Document
Early Estimate Received from CMAR and Reviewed by City Stakeholders
IT Page Turns and Budget Development (DFS5&EMB)
FF&E Budget Development (DFS5&EMB)
Art Package Returned from Art Committee with Comments
Storm Shelter Consultant
50% Budget Review with CMAR
90% Construction Documents
GMP-01 2nd Round of Bids Closed
NEXT STEPS:
GMP-01 to City for Review 02-DEC
EMB Foundation and App Bay Design Changes
Terracon Engineering Services Scope and Contract to CC 17-DEC
Extreme Modular Building Construction Documents to be Approved by State
GMP-01 to CC for Approval Possibly 17-DEC
100% CD Issued for Permitting and Bidding 17-Dec
Extreme Modular Building Construction
Art Package back to CoD Art Committee
Next Estimates (Early December) to Include Changes in Masonry, Roof, and OTS Doors