ACHIEVEMENTS:
FF&E/IT Budget Development
Art Package Submitted to Parks
Storm Shelter Consultant
95% Construction Documents
DFS6 SOV Decision

NEXT STEPS:
Terracon Engineering Services Scope and Contract to PUB FEB
Budget Review CORE/Martinez/City of Denton
Plan Permit Review (In Progress)
Purchasing Review of Bid Package
Legal Advertisement (March)
GMP Creation (April)
GMP to Council (April-May)
Construction (June)