ACHIEVEMENTS:
Material Testing
Final Scoring of CMAR and Selection
CMAR Preconstruction Negotiation
100% Schematic Design complete
NEXT STEPS:
Precon CMAR GMP - City Council Date Pending
Terracon Engineering Services Scope and Contract
100% Extreme Modular Building Construction Doc.
100% Design Documents
50% Construction Documents
100% CD Issued for Permitting and Bidding
Extreme Modular Building Delivery Dec-Jan
GMP to City Council Dec-Jan