Denton, TX
Design/Procurement Phase
Fire House #5 and #6

Design/Procurement Phase

Achievements and next steps

ACHIEVEMENTS:
CORE Bid Package Submitted to City Purchasing for Review
Terracon Engineering Services Scope and Contract Approved by City Council
100% Construction Documents Submitted for Permitting
FF&E Budget Development (DFS6)
Art Package Submitted for Bids
Storm Shelter Consultant
Fiber/DME Resolution
Art Package Submitted for Bids
Storm Shelter Consultant

NEXT STEPS:
Advertise for Bids 5-MAR
Prebid Meeting 12-MAR
Finalize Utilities for Temp Station
Plan Permit Review (In Progress)
GMP Creation (April)
GMP to Council (April-May)
Construction (June)

Stay Informed