Fire Station #5
ACHIEVEMENTS:
Building demoed
Coordination with Bonnie Brae project connections
NEXT STEPS:
Prep site for underground work
Install Underground Sanitary Sewer
Drill piers
Fire Station #6
ACHIEVEMENTS:
Concrete Pours Completed
Began CMU Wall Installation
Steel Beams and Columns has begun
NEXT STEPS:
Complete Steel Work
Begin Framing working
Install Roof decking and roof system