Denton, TX
Construction Progress
Fire House #5 and #6

Construction Progress

Update provided for First Station 5 and Fire Station 6

Fire Station #5
ACHIEVEMENTS:
Sprung Structure Grading
Temp Station Submittals
Domestic Water Line
UG Power Line
Sanitary Sewer Line
Fire 5 Erosion Control/Watershed Inspection

NEXT STEPS:
Temp Station Flex base
Sprung Foundation
Install Sprung Structure
Install OH Doors
Install Electric Underground Feed from Transformer
Install Sanitary Temp (In-Process)
Install Concrete Pads for Generator and Riser Room
Temp Station Interior MEP



Fire Station #6
ACHIEVEMENTS:
100% Piers Complete
Grade Beams (Apparatus Bay) Complete
Grade Beams (Operations Side) Formed
South Storm Sewer 50%

NEXT STEPS:
Pour Grade Beams (Operations Side)
Start Storm Sewer Install
Excavate & Install Water Line
Excavate & Install Storm Line
Excavate & Install Gas Line
Excavate & Install Power Line
Underground MEP (Bay and Ops)
Pour Slab