Design/Procurement Phase
Fire House #5 and #6

Design/Procurement Phase

Achievements and next steps

ACHIEVEMENTS:
All Permitting Documents Submitted to City of Denton for Both Temp and Permanent
Prebid Completed
GMP Creation
ILA Pflugerville/Denton for Temp Trailer Executed

NEXT STEPS:
Finalize Permitting
GMP to the CoD 29-APR Negotiations
GMP to Purchasing for CC Meeting Agenda 5-MAY
GMP to CC 03-Jun
GMP NTP 20-Jun (Temp Facility)
Procurement – Switchgear, Panels, Generator and Structural Steel
Fire Station 5 Construction Start 07-NOV