ACHIEVEMENTS:
50% Construction Documents (City Review)
100% Extreme Modular Building Design Document
Early Estimate Received from CMAR
IT Page Turns and Budget Development (DFS5&EMB)
FF&E Budget Development (DFS5&EMB)
Art Package Returned from Art Committee
Storm Shelter Consultant
NEXT STEPS:
Terracon Engineering Services Scope and Contract to CC 19-NOV
50% Budget Review with CMAR (Meeting 07-NOV)
90% Construction Documents 12-Nov
Extreme Modular Building Construction Documents to be Approved by State
100% CD Issued for Permitting and Bidding 17-Dec
Extreme Modular Building Construction
GMP-01 to Re-Bid 06-NOV
Art Package back to CoD Art Committee