ACHIEVEMENTS:
100% Design Documents
100% Extreme Modular Building Design Document
Early Estimate Received from CMAR and Reviewed by City Stakeholders
50% CD’s 01-Oct
Preconstruction efforts/Site Investigation
FF&E/IT Budgeting Meetings
EMB Foundation Design
CoD Capital Projects Partnering Session for FS5&6 13-Sep
NEXT STEPS:
Terracon Engineering Services Scope and Contract to CC 22-Oct
50% Construction Documents (City Review)
50% Estimates
90% Construction Documents 12-Nov
Extreme Modular Building Construction Documents to be Approved by State
100% CD Issued for Permitting and Bidding 17-Dec
Extreme Modular Building Construction
GMP-01 to CC 22-NOV (EMB/Early Site Work/Gensets)
Project Kickoff 31-Oct
Early Permitting
Acquire Storm Shelter Consulting Service
Art Package to CoD Art Committee