Construction Progress
Fire House #5 and #6

Construction Progress

New update

ACHIEVEMENTS:
Tree Protection, Clearing and Grubbing
Grading
Moisture Conditioning for Pad
Security Fence Complete
Pier Survey
50% Piers Complete
Sprung Structure Procured
Utility Layout for Temp

NEXT STEPS:
Project Submittals Ongoing
50% Pad Left (House, Storm Shelter, Dumpster Pad and Generator Pad Piers)
Start Sanitary Sewer Install
Start Storm Sewer Install
Grade Beam Forms and Excavation Perimeter
Grade Beam Forms and Excavation Interior
Grade Beam Forms and Excavation House
Install RCP and Boxes – Area South
Temp Station Submittals
Temp Station Flex base
Temp Station Trailer MEP
Install Domestic Water Line (In-Process)
Sprung Foundation
Install Sprung Structure
Install OH Doors
Install Electric Underground Feed from Transformer
Install Sanitary Temp (In-Process)
Install Concrete Pads for Generator and Riser Room

Photo of utility layout