ACHIEVEMENTS:
Contract Negotiations
City Council Approval 22-JUL
Permitting Finalized
SWPPP Permit Complete
Temporary Fire Station Trailer Delivered
NEXT STEPS:
Obtain Construction Permit
Kick-Off Meeting 01-AUG
Issue Notice to Proceed 01-AUG
CORE Construction Mobilization 04-AUG
Temp Station Submittals 11-AUG
Temp Station Construction 12-AUG to 30-OCT
Sprung Strructure August -November
Grading 04-AUG
Stay Informed