Denton, TX
Design/Procurement Phase
Fire House #5 and #6

Design/Procurement Phase

Achievements and next steps

ACHIEVEMENTS:
Contract Negotiations
City Council Approval 22-JUL
Permitting Finalized
SWPPP Permit Complete
Temporary Fire Station Trailer Delivered

NEXT STEPS:
Obtain Construction Permit
Kick-Off Meeting 01-AUG
Issue Notice to Proceed 01-AUG
CORE Construction Mobilization 04-AUG
Temp Station Submittals 11-AUG
Temp Station Construction 12-AUG to 30-OCT
Sprung Strructure August -November
Grading 04-AUG